Change Request for Review: Weather Data

As a part of the Interactive Bill MVP launch, weather data will be displayed and available to customers on the customer portal. Today customers are able to also access weather data via Apogee on their energy forecast and bill analysis webpages. To...
almost 2 years ago in CR - T0 0 Submitted

Maximum number of available bills

There is a scenario where a customer receives one bill containing two consecutive periods. The current development of this scenario makes the drop-down list replicate the statement date since we are showing the bill associated with each period. Ac...
almost 2 years ago in A Miss 1 Approved

Tooling Change Mid Inception?

It was discovered that there were meetings discussing moving away from AHA! before completing the inception phase.
about 2 years ago in Idea 0 Abandoned

Cost chart with stacked bars

Present the user with a chart of stacked bars so that he/she can quickly recognize which component contributes the most to his/her billing and see if there has been a change in those that behave like fixed charges (barely change over time), in the...
about 2 years ago in Idea 0 Pending Formal Review

DAP Team Development Effort

Early meetings with the DAP team indicate their availability to start development may not be until late December early January, development estimate for DAP Development effort in progress
about 2 years ago in Risk 0 Monitoring

Early Estimates show Risk to the Release Ready for Transition Milestone

Early Estimates show Risk to the Release Ready for Transition Milestone
about 2 years ago in Risk 0 Monitoring

Start Construction Early!

The idea is to start construction early
about 2 years ago in Idea 0 Abandoned

Release Planning/Management Quality negatively impacted by MiFlow Release 1

Because MiFlow release 1 was not properly ready for rollout at the start of the TECO project, multiple issues stemmed from the release framework not being in place. The abnormally high discovery lag can also be attributed to this.
about 2 years ago in Issue 0 Active

Additional Enablement CR needed

TECO has requested additional enablement training around the following areas: Technical Support of each Infrastructure Component Monitoring tools integration with what TECO is using POC for Solar Winds
about 2 years ago in CR - T2 0 Abandoned

UAT time allocation

We currently allocate 3 weeks to perform User Acceptance Testing, however, this time may not be enough and TECO may require more time due to the different variations we have in the iBill components.
about 2 years ago in Risk 0 Monitoring